Judge: Virginia Keeny, Case: 22VECV00629, Date: 2023-03-01 Tentative Ruling
Case Number: 22VECV00629 Hearing Date: March 1, 2023 Dept: W
WC STRUCTURES,
INC. v. MGAM, INC.
plaintiff/cross-defendant wc
structures, Inc.’s motion to compel further responses
Date of Hearing: March
1, 2023 Trial
Date: None
set.
Department: W Case No.: 22VECV00629
Moving Party: Plaintiff/Cross-Defendant
WC Structures, Inc.
Responding Party: Defendants/Cross-Complainants
MGAM Inc., MGA Electric Corporation dba Trust Electric, and Joshua Manevich
Meet and Confer: Yes.
(Velthoen Decl. ¶¶5-6.)
BACKGROUND
This is a breach of contract cause of action. Plaintiffs
WC Structures, Inc. and William Whitley filed a complaint against Defendants MGAM
Inc., MGA Electric Corporation dba Trust Electric, and Joshua Manevich
asserting causes of action for breach of contract, quantum meruit, and account
stated. Plaintiffs allege Defendant MGAM entered into a written agreement with
National Commercial Construction, Inc. (“NCCI”) to provide rough carpentry for
a residential project. MGAM subsequently entered into a written agreement with
WC Structures to furnish labor and materials as a rough carpentry subcontractor.
However, due to some disputes regarding payment by NCCI, MGAM breached the
agreement by failing to pay WC Structures all amounts due under the contract.
MGAM Inc.
and MGA Electric Corporation dba Trust Electric filed a Cross-Complaint against
WC Structures, Inc. and William Whitley. On October 14, 2022,
Cross-Complainants filed a First Amended Complaint for breach of contract,
breach of the implied covenant of good faith and fair dealing, and fraud. Cross-Complainants
allege William Whitley and WC Structures breached the written agreement by intentionally
misrepresenting the percentage of completion of the framing in its reports to
MGAM and refused to go back to work after MGAM was served with a 48 hours notice
to recommence work. Cross- Complainants further allege Cross-Defendants agreed
to pay half of the court costs and attorney fees incurred by MGAM in its legal
action against NCCI for its failure to pay the final payment.
[Tentative] Ruling
Plaintiff/Cross-Defendant
WC Structures, Inc.’s Motion to Compel Further Responses is GRANTED.
ANALYSIS
Plaintiff/Cross-Defendant
WC Structures, Inc. moves for an order compelling further responses from
Defendant/Cross-Complainant MGAM, Inc. to Plaintiff’s Request for Production of
Documents, Set One Nos. 26, 27, and 28. WC Structures brings the motion on the
grounds that MGAM, Inc., has asserted meritless objections to the Requests for
Production.
Under
Code of Civil Procedure sections 2030.300(a), parties may move for a further
response to requests for production of documents where an answer to the requests
are evasive or incomplete or where an objection is without merit or too
general.¿¿A motion to compel further production must set forth specific facts
showing good cause justifying the discovery sought by the inspection demand.
(See CCP § 2031.310(b)(1).) Notice of the motions must be given within 45 days
of service of the verified response, otherwise, the propounding party waives
any right to compel a further response. (CCP §2030.300(c).) The motions must
also be accompanied by a meet and confer declaration. (CCP
§2030.300(b).)¿¿Finally, Cal. Rules of Court, Rule 3.1345 requires that all
motions or responses involving further discovery contain a separate statement
with the text of each request, the response, and a statement of factual and
legal reasons for compelling further responses. (Cal. Rules of Court, Rule
3.1345(a)(3).)
First,
WC Structures argues MGAM has waived any attorney-client privilege in connection
with the fee agreement and invoices. WC Structures contends because MGAM has
sued Plaintiffs to recover one-half of the legal fees incurred by MGAM in prosecuting
its claim against NCCI for breach of the Framing Subcontract, MGAM has placed
the fee agreements with its attorneys and the invoices on the NCCI litigation
directly at issue. The court agrees.
MGAM,
in opposition, states MGAM has agreed to produce copies of the fee invoices with
attorney-client information redacted therefrom. WC Structures says as of the
date of the reply, however, MGAM has failed to produce such documents. Given
the compelling nature of the invoices, the court orders MGAM to produce the fee
invoices within 30 days. MGAM may redact
actual attorney-client communications but must leave sufficient information for
plaintiff to be able to ascertain the task performed and whether the work was
performed on matters covered by the disputed contract.
Next,
WC Structures argues the confidentiality provision in the settlement agreement does
not bar production. WC Structures contends MGAM sued NCCI for lost profits on the
very same contracts that MGAM now seeks lost profit damages from Plaintiffs.
However, MGAM refuses to disclose its settlement agreement with NCCI.
In
opposition, MGAM argues WC Structures has not made any showing whatsoever to
overcome the privacy interests of the parties to the settlement agreement to
justify production of the confidential settlement agreement. Specifically, if
the terms of the settlement agreement are disclosed it is believed it would harm
the parties with respect to negotiations for other construction contracts and
would be detrimental to other parties covered by the insurance companies. Moreover,
the terms of the settlement agreement have no bearing on the amount that MGAM
owes or does not owe to WC Structures because whether or not MGAM is paid by
NCCI for the framing, MGAM owes WC Structures under the contract for the
percentage of the framing WC Structures actually performed.
Balancing
MGAM’s privacy interests with WC Structures’ interests in disclosure, the court
finds in favor of discovery of the settlement agreement. (See Williams v. Superior
Court (2017) 3 Cal.5th 531, 533.) The settlement agreement may touch upon payments
that would be credited against any alleged damages against WC Structures arising
out of the termination of the contract between MGAM and NCCI. As noted by WC
Structures, MGAM has not provided how this alleged construction dispute would damage
the parties with respect to other parties or their insurers. Moreover, MGAM has
not established WC Structures must legally give third parties’ notice whose privacy
may be invaded if the production is ordered. Accordingly, MGAM is ordered to
provide the settlement agreement within 30 days. The parties should stipulate
to a protective order limiting the disclosure of the settlement agreement. At this point, the court sees no need to
conduct an in camera inspection of the settlement agreement.
Lastly,
WC Structures seeks sanctions in the amount of $1,900 against MGAM. WC
Structures contends MGAM’s objections to the discovery are not only meritless, the
objections signal an attempt to shield evidence that goes to the heart of its
claims against Plaintiffs.
MGAM
contends there should be no question that MGAM’s refusal to produce the agreement
and its opposition to the motion to compel based upon the constitutional right
of privacy is substantial justification for its actions in refusal and
opposition to the motion without a court order. The court agrees. The court
finds MGAM acted with substantial justification in opposing the motion.
Accordingly,
WC Structures’ request for sanctions is DENIED.