Judge: William A. Crowfoot, Case: 19GDCV00389, Date: 2024-08-30 Tentative Ruling
Case Number: 19GDCV00389 Hearing Date: August 30, 2024 Dept: 3
SUPERIOR COURT OF THE STATE OF
CALIFORNIA
FOR THE COUNTY OF LOS ANGELES - NORTHEAST
DISTRICT
I.
INTRODUCTION
On March 27,
2019, this action was filed by James P. Murphy Construction against T.B. Penick
& Sons (“Penick”), Paseo Pasadena Hotel Investment, LLC (“Paseo”), and
CAPREF Paseo LLC (“CAPREF”). This action arises from a dispute related to the
construction of the Hyatt Place Pasadena Hotel (“Hotel”) located at 399 East
Green Street in Pasadena. This action was later deemed related to 15 other
cases and consolidated with 13 of the 15 related cases involving subcontractors
for the Hotel as the parties disputed who bore liability for additional costs which
were incurred during construction. After a series of settlements and
dismissals, the only parties remaining in this litigation are Penick, the
general contractor, and Paseo, the ground leaseholder for the Hotel.
The operative
pleadings are Paseo Pasadena’s cross-complaint (“XC”), filed on May 6, 2019, and
Penick’s First Amended Cross-Complaint (“FACC”) filed on July 29, 2024. In its
cross-complaint against Penick, Paseo alleges that on or around July 6, 2017, it
entered into a prime contract with Penick for the construction of the Hotel
(“Prime Contract”) with a Guaranteed Maximum Price (“GMP”) of $28.15 million,
which was later increased to $30,214,540.55 in a change order approved on
January 1, 2019. Paseo asserts causes of action for declaratory relief, breach
of contract, bad faith, negligence, and breach of fiduciary duty.
As for
Penick’s FACC, Penick alleges that Paseo breached the Prime Contract by failing
and refusing to pay invoices, change orders, claims, and requests for monies
due. Penick also asserts quasi-contract claims for quantum meruit, open book
account, and account stated, along with the foreclosure of a mechanics lien
recorded on the Property and recovery on a mechanics lien bond.
II.
PROCEDURAL
HISTORY
Paseo previously brought a motion for
summary adjudication which was heard and granted by the Honorable Teresa
Sanchez-Gordon in this department. As stated in Judge Sanchez-Gordon’s order,
dated February 18, 2022, Paseo sought and obtained summary adjudication as to
the following issue: “Penick has no, and cannot obtain, written approved change
orders increasing the GMP above $30,214,540.55 and is thus financially
responsible for any additional subcontractor costs.” (2/18/2022 Order, p. 2.) Judge
Sanchez-Gordon added, “[T]he issue here is from which party may the
subcontractors seek payment for services rendered,” noting that “[u]nder the
Prime Contract, Paseo is responsible for payment of subcontractor work up to
the GMP” and work without prior written authorization from Paseo is Penick’s
responsibility. (Order, p. 5.) Due to the limited scope of the issue presented
by the motion, Judge Sanchez-Gordon rejected Penick’s argument that the GMP was
increased due to additional subcontractor costs because written notice prior to
performing work was required if Penick wanted to increase the GMP and there was
no evidence that Penick provided such written notice.
On December 21, 2022, the Honorable
Colin P. Leis issued an order pursuant to stipulation that Judge
Gordon-Sanchez’s ruling did not resolve several issues raised by Penick in its
opposition brief. (12/21/2022 Order, p. 7.) These issues include: waiver,
Penick’s claims due to Paseo’s allegedly misleading plans and specifications, and
whether the contract between Paseo and Penick was abandoned.
On June 13, 2024, Paseo filed a motion
for summary judgment against Penick on Penick’s FACC. Paseo argues that Penick
is not entitled to any additional payment over and above the GMP because no
written notice was provided before the work at issue was performed.
On June 21, 2024, Penick filed a motion
for summary adjudication of Paseo’s noncontract claims as well as Paseo’s
claims for consequential damages.
III.
LEGAL STANDARD
In reviewing a motion for summary
judgment, courts must apply a three-step analysis: “(1) identify the issues
framed by the pleadings; (2) determine whether the moving party has negated the
opponent’s claims; and (3) determine whether the opposition has demonstrated
the existence of a triable, material factual issue.” (Hinesley v. Oakshade Town Center (2005) 135 Cal.App.4th 289, 294.) “Once
the defendant . . . has met that burden, the burden shifts to the plaintiff . .
. to show that a triable issue of one or more material facts exists as to the
cause of action or a defense thereto.” (Code Civ. Proc., § 437c, subd. (p)(2).)
The plaintiff may not merely rely on allegations or denials of its pleadings to
show that a triable issue of material fact exists, but instead, “shall set
forth the specific facts showing that a triable issue of material fact exists
as to the cause of action.” (Ibid.)
“If the plaintiff cannot do so, summary judgment should be granted.” (Avivi v. Centro Medico Urgente Medical
Center (2008) 159 Cal.App.4th 463, 467.)
“A party may move for summary
adjudication as to one or more causes of action within an action, one or more
affirmative defenses, one or more claims for damages, or one or more issues of
duty, if that party contends that the cause of action has no merit or that
there is no affirmative defense thereto, or that there is no merit to an
affirmative defense as to any cause of action, or both, or that there is no
merit to a claim for damages . . . or that one or more defendants either owed
or did not owe a duty to the plaintiff or plaintiffs. A motion for summary
adjudication shall be granted only if it completely disposes of a cause of
action, an affirmative defense, a claim for damages, or an issue of duty.”
(Code Civ. Proc., § 437c, subd. (f)(1).) A motion for summary adjudication
shall proceed in all procedural respects as a motion for summary judgment. (Id., subd. (f)(2).)
IV.
PASEO’S
MOTION FOR SUMMARY JUDGMENT
Penick and Paseo do not dispute the
general events underlying this action. The parties agree that on or about July
6, 2017, Paseo retained Penick to act as the general contractor on the Project
by entering into an American Institute of Architects (“AIA”) Form A102- 2007
and A201-2007 written contract (“Prime Contract”). (UMF No. 1.) The parties
also agree that pursuant to the Prime Contract, all change order work must be
approved by Paseo in writing prior to the commencement of the work. (UMF No.
3.) Additionally, the parties agree that the GMP for the Prime Contract was initially
$28,150,000 but, as of the last executed Prime Contract Change Order (PCCO) No.
15, dated December 17, 2018, the GMP was increased to $30,214,540.55. (UMF Nos.
2, 18.) Last, the parties do not dispute that Penick does not have any executed
PCCOs other than PCCO No. 15. (UMF No. 19.)
A.
Evidentiary
Objections
The Court disregards Paseo’s objections
to the Declarations of Tim Penick, Rich Petersen, Tony Lee, Michelle Mangan
because those declarations were not submitted with Penick’s opposing papers.
The Court OVERRULES Paseo’s objections to the declarations of Matt Adams and
Phillip McDowell. Both experts premise
their opinions on admissible documents including construction documents, change
orders, and construction schedules.
B.
Paseo’s
Moving Papers
“To prevail on a cause of action for
breach of contract, the plaintiff must prove (1) the contract, (2) the
plaintiff’s performance of the contract or excuse for nonperformance, (3) the
defendant’s breach, and (4) the resulting damage to the plaintiff.” (Richman
v. Hartley (2014) 224 Cal.App.4th 1182, 1186.)
Penick alleges that Paseo breached the
Prime Contract by “failing and refusing to pay Penick’s invoices, change
orders, claims and requests for monies incurred by Penick which are due and
owing to Penick as required by the Prime Contract.” (FACC, ¶ 12.) Penick
contends that it has incurred at least $5,215,836 in damages. (FACC, ¶ 13.)
First, Paseo argues that Penick’s
breach of contract claim fails because it is not required to pay Penick
anything over and above the GMP, which was already determined to be
$30,214,540.55 by Judge Sanchez-Gordon. Paseo submits the declaration of Conrad
Garner, its “representative” who states that Paseo’s business records show that
Paseo paid Penick $26,552,066, in addition to paying $3,262,942 to
subcontractors who should have been paid by Penick but were not. (Paseo’s Ex.
O, ¶¶ 2-3.) Therefore, Paseo states, a total of $30,295,818 has been paid to
Penick and subcontractors, which exceeds the GMP. Paseo contends that Penick is
not entitled to additional money due to any “Claims” because Judge
Sanchez-Gordon already found that no written approval was obtained before the
work at issue in those “Claims” was performed, and prior written approval was
necessary to increase the GMP.
Second, Paseo argues that Penick cannot
recover under quantum meruit or the asserted common counts because there was no
understanding or expectation that Penick would be compensated for more than the
GMP, nor was there any relationship other than the Prime Contract. “To recover
in quantum meruit, a party need not prove the existence of a contract
[citations], but it must show the circumstances were such that ‘the services
were rendered under some understanding or expectation of both parties that
compensation therefor was to be made.’ [Citation.] (E. J. Franks
Construction, Inc. v. Sahota (2014) 226 Cal.App.4th 1123, 1127–1128.)
Last, Paseo argues that the Prime
Contract establishes the amount it is obligated to pay Penick and therefore precludes
Penick’s mechanic’s lien or any recovery on the Mechanic’s Lien Release Bond.
C.
Penick’s
Opposition
In opposition, Penick contends that an
issue of fact remains as to whether the plans and specifications provided by
Paseo breached the implied warranty that the plans are correct. (Opp., p. 8.)
Penick claims that the factfinder must determine whether Paseo breached its
implied warranty of correctness, and whether this breach of contract entitles
Penick to additional compensation.
The Court finds this argument
unavailing, however. As previously determined by Judge Sanchez-Gordon, the
Prime Contract establishes a procedure by which Penick was supposed to submit a
request for an increase to the GMP and which required prior written approval.
Accordingly, if Penick determined that there were issues with the plans and
specifications which would have increased its costs, Penick would be able to
assert a claim for an increase in the GMP. It is undisputed that none of the
work for which Penick requests compensation was performed with prior written
authorization. Therefore, Penick’s claim for damages pursuant to the terms of
the Prime Contract fails.
As an alternate theory of recovery,
however, Penick argues that it may recover under quantum meruit because triable
issues of fact exist as to whether Paseo abandoned the Prime Contract’s scope
and provisions for extra work, and consequently, the GMP. (Opp., p. 10.) In C.
Norman Peterson Co. v. Container Corp. of Am. (1985) 172 Cal.App.3d 628, 640
(“Peterson”), the Court of Appeal affirmed the trial court’s finding
that the owner had breached a construction contract and, as a result of the
owner’s breach and abandonment of the contract, the contractor was entitled to
recover the reasonable value of the work it performed on a quantum meruit
basis, without being limited by the original contract amount. The Peterson court
stated: “In the specific context of construction contracts . . ., it has been
held that when an owner imposes upon the contractor an excessive number of
changes such that it can fairly be said that the scope of the work under the
original contract has been altered, an abandonment of the contract properly may
be found. [Citations.] In these cases, the contractor, with the full approval
and expectation of the owner, may complete the project. [Citations.] Although
the contract may be abandoned, the work is not. Under this line
of reasoning, the trial court was well justified in determining that, by their
course of conduct, the parties had abandoned the terms of the written contract
while proceeding to complete the [] project.” (Peterson, 172 Cal.App.3d
at p. 640.) The Peterson court cited to Opdyke & Butler v. Silver
(1952) 111 Cal.App.2d 912 (“Opdyke”), in which the parties disputed
whether, during the course of performance, the written agreement with a maximum
limit as to costs had been an abandoned and an oral agreement substituted for
it. (Peterson, supra, 172 Cal.App.3d at p. 640.) The Peterson
court noted that in Opdyke, the owner “constantly changed his mind
concerning the construction, and the completed project differed markedly from
the original plans and specifications.” (Ibid.) The Peterson court
further noted that the appellate court in Opdyke “enumerated 20 changes
which materially increased the contractor’s costs and caused performance of the
work to be done under disadvantageous circumstances.” (Id. at p. 641.) Turning
to the case before it, the Peterson court drew comparisons to the facts
in Opdyke, pointing out that there was “evidence of hundreds of changes,
many of them significant, resulting in extra work having to be performed by
[the contractor].” (Ibid.) Additionally, “as in Opdyke, the
requirement for written change orders was ignored during most of the project
period, and it was completely abandoned during the critical shutdown stage.
Similarly, in Daugherty Co. v. Kimberly-Clark
Corp. (1971) 14 Cal.App.3d 151, 155, an owner’s changes resulted in a
nearly $3 million dollar increase to a contract price because the project was
“completely redesigned” and an experienced manager stated “he had never seen
anything comparable to the changes ordered by the owner, the project was the
most poorly engineered he had ever seen, and this resulted in the enormous
change orders.” The Daughterty court concluded that due to numerous
changes, a triable issue existed “as to whether the contract had been abandoned
by the parties.”
Relying on this collection of cases, Penick
argues that Paseo abandoned the contract. Penick cites to various potential
change orders and applications for payment in support of its claim that on
multiple occasions, Paseo approved change orders for work and paid for work
that was performed prior to written authorization being obtained from Paseo.
(AMF Nos. 35-36.) Penick also cites to the deposition testimony of Rogers
Stevenson, who identifies himself as Paseo’s representative and testified in
deposition that it was customary for him to approve work over the phone and
have Penick send emails afterwards to keep a record of the authorization.
(Penick’s Ex. 3, p. 121:10-20.) Rich Peterson, Penick’s PMQ, testified that as
project manager, he had an understanding that all change orders had to be
approved by Paseo in writing before work commenced, but that this understanding
changed when Paseo’s management “gave [him] direct verbal [sic] on certain
items to just get them done and submit the paperwork to avoid delay of the
project.” (Paseo’s Ex. 3, 30:14-25.)
Penick also submits the declaration of
Matt Adams (“Adams”). Adams identifies himself as the principal of Devcon CPM
LLC and states that he has: (1) 40 years of experience with respect to
construction management services and (2) significant experience consulting as
an owner’s representative in connection with construction projects. (Adams
Decl., ¶ 3.) Adams states that at least 179 of Penick’s claims were based on changes
to the original scope of work with a value of approximately $1.3 million and
that these changes affected nearly every trade involved in the project from
drywall to mechanical to electrical. (Adams Decl., ¶¶ 8-9.) Adams opines that scope
changes of this quantity, type and magnitude are “excessive” and “have the
effect of fundamentally impacting both a contractor’s costs and its time for
performance of work.” (Adams Decl., ¶ 10.)
Penick also
submits the expert declaration of Phillip McDowell, who declares that he has
significant experience with the forensic analysis of construction schedules and
evaluation of project delays. (McDowell Decl., ¶ 3.) He states that he has
analyzed the project delays that occurred during the construction project and determined
that there were at least 141 days of excusable delays for which Penick was owed
extensions of time to complete its work, and that Penick managed to mitigate at
least 105 days, which amounts to a 75% reduction in project delay, despite a
33% increase in project duration. (McDowell Decl., ¶¶ 12, 14.) McDowell states that the increase in project
duration, followed with acceleration to reduce any resulting delays by 75% is a
significant change that fundamentally affects a contractor’s costs. (McDowell
Decl., ¶ 15.)
D.
Paseo’s
Reply
In its reply brief, Paseo argues that
Penick is precluded from arguing that the Prime Contract was abandoned because
the issue was not raised in its original cross-complaint, or FACC. (Reply, pp.
3-4.) However, Penick asserted a claim for quantum meruit, which would only
apply if the contract was abandoned. Paseo also claims that Penick has never
raised the issue of abandonment in this litigation, which is a patently untrue
statement. In 2022, Penick argued on pages 12 and 13 of its brief in opposition
to Paseo’s previous MSA that Paseo waived the requirement for prior written
authorization for additional work. Also, on page 15 of Penick’s brief, the heading
for Section IX states: “THERE ARE TRIABLE ISSUES OF MATERIAL FACT REGARDING
WHETHER THE CONTRACT WAS ABANDONED.” The parties additionally stipulated that
the issues of waiver or abandonment were not encompassed by Judge
Sanchez-Gordon’s ruling; therefore, Paseo’s argument that Penick is not
entitled to additional payment under the Prime Contract due to a prior ruling is
unavailing. Paseo’s argument that the terms of the Prime Contract prohibit
recovery on the theory of abandonment is also unpersuasive because the theory
of abandonment would render the terms of the Prime Contract irrelevant. Furthermore,
the Court additionally notes that Paseo’s “response” to Penick’s additional
material facts appears to be responding to an entirely different document because
its responses do not correspond with any of the additional material facts
listed in Penick’s Separate Statement.
Based on the evidence submitted by
Penick, triable issues of material fact exist regarding whether the Prime
Contract was abandoned and whether Penick is entitled to recover the reasonable
value of its services under quantum meruit. Accordingly, Paseo’s motion for
summary judgment is DENIED.
V.
PENICK’S MOTION FOR SUMMARY
ADJUDICATION
Penick moves for summary adjudication
on Paseo’s noncontract claims and Paseo’s claim for consequential damages. As
an initial matter, Penick cannot seek summary adjudication on a claim for
consequential damages. Code of Civil Procedure section 437c(f)(1) states, in
relevant part: “A party may move for summary adjudication as … one or more
claims for damages, … if the party contends that … there is no merit to a claim
for damages, as specified in Section 3294 of the Civil Code.” In DeCastro
West Chodorow & Burns, Inc. v. Superior Court (1996) 47 Cal.App.4th
410, 412, the court of appeal affirmed a trial court’s denial of a motion for
summary adjudication of the plaintiff’s “lost opportunity” damages. The
appellate court stated that a “single item of compensatory damage which does
not dispose of an entire cause of action” is not a proper subject for summary
adjudication. (Id. at p. 422.) Here, Penick concedes that it is not
seeking to summarily adjudicate Paseo’s contract claim and does not identify
any particular breach of contract which could be a deemed a basis for summary
adjudication as a separate cause of action. (See Lilienthal & Fowler v.
Superior Court (1993) 12 Cal.App.4th 1848.) Therefore, the motion is DENIED
as to Paseo’s claims for consequential damages.
The remainder of Penick’s motion
addresses Paseo’s noncontract claims for bad faith, negligence, and breach of
fiduciary duty. Penick essentially argues that Paseo cannot assert a basis for
tort liability because all of Paseo’s claims arise from their contractual
relationship under the Prime Contract. However, as stated above, the Court
finds that Penick raises a triable issue of fact as to whether the Prime
Contract was abandoned. Therefore, Penick cannot bar Paseo’s tort claims by
hiding behind a contract that it claims was abandoned by both parties. Accordingly,
Penick’s motion for summary adjudication is DENIED.
VI. CONCLUSION
In light of
the foregoing, Paseo’s motion for summary judgment is DENIED. Penick’s motion
for summary adjudication is DENIED.
Moving party to give notice.
Dated
this
|
|
|
|
|
William A. Crowfoot Judge of the Superior Court |
Parties who intend to submit on this
tentative must send an email to the Court at ALHDEPT3@lacourt.org indicating
intention to submit on the tentative as directed by the instructions provided
on the court website at www.lacourt.org.
Please be advised that if you submit on the tentative and elect not to appear
at the hearing, the opposing party may nevertheless appear at the hearing and
argue the matter. Unless you receive a
submission from all other parties in the matter, you should assume that others
might appear at the hearing to argue. If
the Court does not receive emails from the parties indicating submission on
this tentative ruling and there are no appearances at the hearing, the Court
may, at its discretion, adopt the tentative as the final order or place the
motion off calendar.